2013
November

Grass field at Kyle Field removed.

First deck on east side and Netum Steed Strength and Conditioning Laboratory demolished.

Concrete pillars and piers for south end zone addition are poured.

December

Steel support structures erected.

Columns supporting east-side canopy are being erected.

Northeast tower (with escalators and stairs) is being constructed.

2014
January-May

South end zone concrete risers placed on steel support structures.

Northeast plaza and re-paving of Houston Street begins

June

Precast brick facades, glass, exterior, skin, and three scoreboards placed around stadium walls.

August

First phase of redevelopment nears completion.

November-December

North-end plaza demolition and controlled collapse of the west side of Kyle Field.

2015
January

Clearing of debris to makeroom for entire new west side.

February-June

Erection of three new decks of Kyle Field.

June-August

Finish-out of suites and clubs for west side

September

Opening of the redeveloped Kyle Field.